Profit testing compresses a year-by-year projection into a handful of decision numbers. The board wants one figure to accept or reject a product, and you need to know which figure answers which question.
Run a year-by-year projection for one policy assumed in force at the start of each year. For year , collect the premium, pay expenses, earn interest on the fund, pay death claims, and release the reserve for survivors. The end-of-year balance is the profit vector entry.
Here is the held reserve per in-force policy, the premium at start, start-of-year expense, the earned interest assumption, the death benefit, claim settlement cost, and the end-of-year reserve. The entry captures issue-time outflows (commission, underwriting) that occur before year 1 begins.
KEY: is conditional on the policy being in force at . To get the cash an insurer expects per policy ISSUED, you must weight by survival.
Common mistakes
- Forgetting survival weighting. Reporting directly as the signature ignores that not every issued policy is in force at year-start. Always multiply by .
- Discounting at the earned rate. NPV uses the risk discount rate , not the asset earned rate . The hurdle rewards shareholders, not the bond portfolio. Mixing them up typically inflates NPV by 30 to 100 percent.
- Confusing IRR with hurdle. IRR is computed from the signature; the hurdle is set by the insurer. The accept rule is IRR > hurdle, never the other way.
Bottom line
- Profit vector is end-of-year cash per policy in force at start of year ; profit signature is per policy issued and is the series you discount.
- NPV discounts at the risk discount rate , never the earned rate ; accept when NPV > 0. The roll-up inside uses .
- The hurdle exceeds the earned rate because shareholders demand a return above the asset yield.
- IRR solves ; accept when IRR exceeds the hurdle . Multiple sign flips in can yield several IRRs, so prefer NPV.
Exam shortcut
Build one cumulative-discounted column from the signature. Read NPV as the last entry; read DPP as the first non-negative row. Two metrics, one computation. DECISION: Single hurdle rate given, ranking absolute profit → use NPV and DPP. Comparing contracts of very different sizes → use profit margin or IRR. For quick IRR, find two trial rates that bracket NPV = 0 and linearly interpolate.
The full lesson (about 11,513 words, 77 min read) adds 7 worked examples, all 15 common mistakes, a self-check, free in the app.
Learning objectives
- 4c
Browse all free Exam ALTAM lessons or jump into free Exam ALTAM practice questions.